The African data center buildout 2026: Lagos, Nairobi, Cape Town, and Cairo
Africa hosts roughly 1.5 percent of global colocation capacity but is on track to triple installed megawatts by 2028, with Lagos, Nairobi, Cape Town, and Cairo absorbing the bulk of new builds and forcing fresh thinking on power, regulation, and inference latency.
African data center capacity is finally inflecting in 2026. Installed colocation power across the continent now sits near 700 megawatts, still a small share of the global 55 gigawatt market, but contracted pipelines suggest a path to roughly 1.8 gigawatts by 2028. South Africa, Nigeria, Kenya, Egypt, and Morocco anchor that growth. The st...